NASA’s Continuing Lack of Accounting Controls
Jed Margolin
1. In 2002 GAO assessed NASA’s financial
management system as inadequate, but NASA was working on a new financial
management system (its third attempt) and expected it to be fully functional in
2008. It hasn’t happened even though, for a time, NASA’s administrator was an
accountant (Sean O’Keefe - December 2001 to February 2005).
Reference 1 - GAO Testimony Before the Committee on Science,
Subcommittee on Space and Aeronautics, House of
Representatives, NASA MANAGEMENT CHALLENGES, Human Capital and Other Critical
Areas Need to be Addressed, Statement of David M. Walker, Comptroller General
of the United States,
July 18, 2002.
http://www.dtic.mil/cgi-bin/GetTRDoc?AD=ADA404576&Location=U2&doc=GetTRDoc.pdf
{Click here for Local Copy}
From page 23 - page 24 (I have underlined what I think is important):
The inadequacy of NASA’s financial management
system has further impact. Without a more effective financial management
system, NASA will likely continue to have difficulty providing relevant,
reliable, timely financial data -including cost information- that can be used
on a real-time basis by program managers to monitor costs, schedule, and
performance. In March 2002, we testified9 that NASA was unable
to provide us with detailed support for amounts obligated against cost limits
established by the fiscal year 2000 NASA Authorization Act. This was due, in
large part, to NASA’s lack of a modern, integrated financial management system.
To its credit, NASA is working toward implementing
an integrated financial management system that it expects to be fully
operational in fiscal year 2008 at an estimated cost of $691 million. This
is NASA’s third attempt toward implementing a new integrated financial
management system. The first two efforts were abandoned after 12 years and
after spending a reported $180 million. NASA’s current approach focuses on
learning from other organizations’ successes in implementing similar projects,
as opposed to revisiting its own failures. NASA has also abandoned the single
product approach that the two prior attempts had as their basic architecture.
Instead, the project will be broken down into implementable modules on the
basis of the availability of proven software products.
2. In January 2004, the
independent auditor -PricewaterhouseCoopers- conducting NASA’s audit pursuant
to the Chief Financial Officers Act and under the direction of the Office of
Inspector General, determined that it could not render an opinion on NASA’s
financial statements for FY 2003. The disclaimer resulted from NASA’s inability
to provide the auditor with sufficient evidence to support the financial
statements and complete the audit within time frames the Office of
Management and Budget established. The disclaimer on the FY 2003 financial
statements followed an unqualified1 FY 2002 audit opinion and a
disclaimed audit opinion in FY 2001.
Reference 2 - Testimony of NASA Inspector General, May 19, 2004
http://oig.nasa.gov/congressional/Testimony051904.pdf {Click here for Local Copy}
Before the
Government Reform Subcommittee on Government Efficiency and Financial Management
U.S. House of Representatives, May 19, 2004, NASA Financial Management
Statement of The Honorable Robert W. Cobb, Inspector General National
Aeronautics and Space Administration.
From page 2:
OVERALL
SUMMARY
In
January 2004, the independent auditor—PricewaterhouseCoopers—conducting
NASA’s audit pursuant to the Chief Financial Officers Act and under the
direction of the Office of Inspector General, determined that it could not
render an opinion on NASA’s financial statements for FY 2003. The disclaimer
resulted from NASA’s inability to provide the auditor with sufficient
evidence to support the financial statements and complete the audit within
time frames the Office of Management and Budget established.
The
disclaimer on the FY 2003 financial statements followed an unqualified1 FY 2002 audit opinion and a disclaimed audit
opinion in FY 2001. The FY 2002 unqualified opinion was the consequence of
a so-called “heroic” effort of the independent auditor PricewaterhouseCoopers.
A heroic audit effort occurs where assurance on the financial statements is
established through substantially expanded transaction testing rather than the
auditor placing reliance on systems of internal control. Such a heroic effort
was not possible in FY 2003 because of dependency on a new automated financial
management system.
The reports that the independent auditor submitted
identified instances of non-compliance with generally accepted accounting
practices, material weaknesses in internal controls, and non-compliance with
the Federal Financial Management Improvement Act. Many of the weaknesses the
audit disclosed resulted from a lack of effective internal control procedures
and problems with NASA’s conversion during FY 2003 from 10 separate systems to
a new single integrated financial management program (IFMP).
Mr. Cobb’s testimony was in 2004.
An article
in the Orlando Sentinel on November 20, 2006 by Michael Cabbage,
Sentinel Space Editor, sheds some light on NASA’s accounting problems. Investigators from the Department of Housing and Urban
Development were called in to conduct an inquiry into complaints made by career
employees in Cobb’s own office. (I wonder why HUD conducted the investigation
and not DOJ.)
From the Orlando
Sentinel article:
According to the probe, the number
of audit reports issued by Cobb's office plummeted from 62 in 2000 to seven
during the first half of the 2006 fiscal year. An audit safety team was
abolished. Investigations were derailed, witnesses said, including some related
to safety and national security.
Investigators found that Cobb lunched, drank, played golf and traveled with
former NASA Administrator Sean O'Keefe, another White House appointee. E-mails
from Cobb showed he frequently consulted with top NASA officials on
investigations, raising questions about his independence.
.
.
.
Nicknamed "Moose," Cobb
came to NASA in April 2002 after 15 months as an ethics lawyer in the Bush
White House responsible for vetting financial-disclosure and
conflict-of-interest issues for administration nominees who required Senate
confirmation. He replaced Roberta Gross, a Clinton appointee, who had been in the job
since 1995 and had earned a reputation on Capitol Hill as a competent,
independent investigator.
The HUD report discusses Gross' departure from NASA.
Gross had contracted with the accounting firm Price Waterhouse Coopers to do
NASA's chief financial audit, investigators wrote. After the White House tapped
O'Keefe to succeed longtime NASA Administrator Dan Goldin in December 2001,
O'Keefe told Gross he was unhappy with the audit. "Gross subsequently
[was] asked to resign," the report said.
Cobb replaced Gross four months after O'Keefe's arrival and canceled the
contract with Price Waterhouse Coopers.
HUD investigators heard testimony from other witnesses that suggested O'Keefe's
and Cobb's association went beyond the traditional arm's-length relationship
between agency heads and inspectors general. E-mail traffic between Cobb,
O'Keefe and former NASA General Counsel Paul Pastorek indicated Cobb consulted
with them on audits and investigations.
.
.
.
In one case, Cobb was accused of
squelching part of an audit related to the international space station program
after conferring with Pastorek. The report notes that investigators found an
e-mail where Pastorek wanted to discuss the audit and questioned its analysis
and conclusions. Investigators wrote that auditors were told to remove all of
the findings from one section, reducing four pages of findings in the draft
report to one paragraph in the final version.
.
.
.
According to witnesses in the HUD
report, Cobb told his staff, as well as an outside group, that he had to do
some "diving saves" to keep his auditors from embarrassing NASA.
See http://www.orlandosentinel.com/news/space/orl-nasa-inspector-files7,0,3895863,full.story
{Click here for Local Copy}
Mr. Cobb protested his innocence.
Despite calls by Senator Jay Rockefeller (D-WV) and Senator Bill Nelson
(D-FL) for Cobb to resign, he refused to do so until April 2009.
http://commerce.senate.gov/public/index.cfm?p=PressRoom&ContentType_id=77eb43da-aa94-497d-a73f-5c951ff72372&Group_id=505cc3fa-a767-40f4-8ac2-4b8326b44e94&MonthDisplay=4&YearDisplay=2009
COMMERCE CHAIRMAN ROCKEFELLER’S STATEMENT ON
RESIGNATION OF NASA INSPECTOR GENERAL ROBERT COBB
Jena Longo - Democratic Deputy
Communications Director 202.224.7824
Apr 02 2009
COMMERCE CHAIRMAN ROCKEFELLER’S STATEMENT ON
RESIGNATION OF NASA INSPECTOR GENERAL ROBERT COBB
WASHINGTON, D.C. – Senator John D (Jay)
Rockefeller IV (D-WV), Chairman of the U.S. Committee on Commerce, Science and
Transportation, issued the following statement regarding the resignation of
NASA Inspector General Robert Cobb:
“Only a few short weeks ago, Senator McCaskill and
I expressed deep concerns to President Obama that the NASA Inspector General,
Robert Cobb, had been repeatedly accused of stifling investigations,
retaliating against whistleblowers and prioritizing social relationships with
top NASA officials over proper federal oversight. I respectfully asked that the President take
immediate action to put an end to IG Cobb’s conflict of interest and cronyism
and remove him from the system.
“News of Robert Cobb’s resignation is certainly
welcome and this is an important step forward.
I applaud the White House for taking a zero tolerance approach to lax
enforcement and oversight. President
Obama is setting the tone from the top and holding all employees who serve the
American people accountable for improper conduct and just plain not doing their
jobs. The time has come to close the
door on this troubling chapter for NASA and a fresh start awaits.”
***(SEE ATTACHED LETTER)***
###
If you want to know what it was like to work for Cobb see the Oral
Statement made to the Oversight Review of the Investigation of the NASA
Inspector General Mr. Robert W. Cobb by Lance G. Carrington
,
Former Assistant Inspector General for Investigations, NASA Office of
Inspector General:
http://legislative.nasa.gov/hearings/2007%20hearings/6-7-07%20carrington.pdf {Click here for Local Copy}
Here is more from the hearings: http://www.agiweb.org/gap/legis110/nasa_hearings.html#june7
The reason for including this material here is because the problems
Cobb reported in his testimony to Congress in 2004 were problems that he
himself created or was complicit in creating.
3. In 2008 NASA was unable to account for capital
assets with an acquisition cost of about $32 Billion (with a net value of about
$18.6 Billion). It was worse than that.
As part of its FY 2007 report on NASA’s financial statement,
E&Y, in its “Report on Internal Control,” dated November 13, 2007,
identified significant deficiencies that it considered to be material
weaknesses under standards established by the American Institute of Certified
Public Accountants. E&Y identified material weaknesses in NASA’s controls
for financial systems, financial analyses, oversight used to prepare the
financial statements, and
processes for assuring that PP&E and materials are presented fairly in the
financial statements. In addition, E&Y stated that NASA’s financial
management systems are not substantially compliant with the Federal Financial
Management Improvement Act (FFMIA) of 19962 noting that certain subsidiary systems, including all
property systems, are not integrated with NASA’s Systems Applications and
Products (SAP) Core Financial module. Core Financial—customized off-the-shelf
software that serves as the backbone to the IEMP—is used to record accounting
transactions including commitments, obligations, and expenditures and to
produce NASA’s annual financial statements
.
Reference 3
-
Report No. IG-08-032 - http://oig.nasa.gov/audits/reports/FY08/IG-08-032.pdf {Click here for Local Copy}
September 25, 2008
TO: Chief Financial Officer
Chief Information Officer
Deputy to Chief Information Officer
Director, Marshall Space
Flight Center
FROM: Assistant Inspector General
for Auditing
SUBJECT: Final Memorandum on NASA’s
Development of the Integrated Asset Management – Property, Plant, and Equipment
Module to Provide Identified Benefits (Report No. IG-08-032; Assignment No.
A-08-001-00)
From page 1:
The Office of Inspector General conducted an audit of NASA’s Integrated
Asset Management – Property, Plant, and Equipment (IAM/PP&E) module. A component of NASA’s Integrated Enterprise
Management Program (IEMP), the IAM/PP&E module is an automated asset-management
system that performs two main functions: equipment management (logistics) and
asset accounting (finance) and was designed to integrate logistics and
financial processes to account for and facilitate management of NASA personal
property.
From page 2:
Executive Summary
We found that NASA adequately
defined the IAM/PP&E module project requirements to ensure the six benefits
are achieved and that the achievement would be measurable. To determine
that the project requirements were adequately defined, we verified that the
requirements were crosswalked to each anticipated benefit; we verified that
project personnel had reviewed the Federal financial system requirements and
could trace the project requirements to the Federal requirements; and we reviewed
the project’s Performance Measurement Plan to verify that a performance measure
could be tied to each of the six identified benefits. We determined that the
IAM/PP&E module, as designed, and the corresponding changes in NASA’s
business processes and controls should help mitigate deficiencies reported as
material weaknesses by Ernst and Young (E&Y), the independent public
accounting firm that conducted the audit of NASA’s financial statements for the
past 4 years.
However, also from page 2:
We note, however, that the
system’s contribution to improved financial reporting may be limited by
inaccurate data. NASA did not validate approximately 6,300 records of capital
assets that have an acquisition value of $32 billion (and a net value of
approximately $18.6 billion) prior to transferring the data into IAM/PP&E.
In addition, NASA has not resolved an operating policy issue involving
identifying purchases of controlled equipment, which could bear on the
successful operations of the system. However, we did not conduct audit work to
address the impact of these issues because E&Y plans to perform tests of
the IAM/PP&E module and NASA’s corresponding manual controls as part of the
fiscal year (FY) 2008 financial statement audit. Accordingly, we made no
recommendations for management action. We issued a draft of this memorandum on
September 17, 2008, and provided NASA management an opportunity to comment on
the draft, but comments were not required and no formal comments were received.
And, from page 2 - page 3
Background
As part of its FY 2007 report on
NASA’s financial statement, E&Y, in its “Report on Internal Control,” dated
November 13, 2007, identified significant deficiencies that it considered to
be material weaknesses under standards established by the American Institute of
Certified Public Accountants. E&Y identified material weaknesses in
NASA’s controls for financial systems, financial analyses, oversight used to
prepare the financial statements,
and processes for assuring that PP&E and materials are presented fairly in
the financial statements. In addition, E&Y stated that NASA’s financial
management systems are not substantially compliant with the Federal Financial
Management Improvement Act (FFMIA) of 1996,2 noting that certain subsidiary systems, including all
property systems, are not integrated with NASA’s Systems Applications and
Products (SAP) Core Financial module. Core Financial—customized off-the-shelf
software that serves as the backbone to the IEMP—is used to record accounting
transactions including commitments, obligations, and expenditures and to
produce NASA’s annual financial statements.
Therefore,
NASA’s response to the criticism that it is not following the accounting
procedures established by the American Institute of Certified Public
Accountants was to cook the books.
4.
FY 2009 was not much better. From Acting Inspector General Thomas J.
Howard:
“Although much progress has been made in developing
policies, procedures, and controls to improve NASA’s financial processes and
systems, challenges remain. Specifically, during FY 2009, NASA management and
Ernst & Young LLP (E&Y) continued to identify deficiencies in the
Agency’s system of internal control, which impair NASA’s ability to timely
report accurate financial information. The most severe deficiency involves
NASA’s internal control over legacy property, plant, and equipment (PP&E).
As shown in the following table, this deficiency has been reported as a
material weakness for several years.”
Reference 4 - NASA 2009 Management
Challenges http://oig.nasa.gov/NASA2009ManagementChallenges.pdf {Click here for Local Copy}
Cover
Letter:
November 13, 2009
TO: Administrator
FROM: Acting Inspector General
SUBJECT: NASA’s Most Serious Management and Performance
Challenges
As required by the Reports Consolidation Act of 2000, this
memorandum provides our views of the most serious management and performance
challenges facing NASA and is to be included in the Agency’s Performance and
Accountability Report for fiscal year 2009.
In determining whether to report an issue as a challenge,
we consider the significance of the issue in relation to the Agency’s mission;
its susceptibility to fraud, waste, and abuse; whether the underlying problems
are systemic; and the Agency’s progress in addressing the issue. We provided a
draft copy of our views to Agency officials and considered all comments
received.
Through various Agency initiatives and by implementing
recommendations made by the Office of Inspector General (OIG) and other
evaluative bodies, such as the Government Accountability Office, NASA is
working to improve Agency programs and operations. However, challenges remain
in the following areas:
• Transitioning from the Space Shuttle to the Next
Generation of Space Vehicles
• Managing Risk to People, Equipment, and Mission
• Financial Management
• Acquisition and Contracting Processes
• Information Technology Security
During FY 2010, the OIG will continue to conduct work that
focuses on NASA’s efforts to meet these challenges as part of our overall
mission to promote the economy and efficiency of the Agency and to root out
fraud, waste, abuse, and mismanagement.
We hope that you find our views helpful. Please contact me
if you have questions.
signed
Thomas J. Howard
From
page 5 - page 6:
Financial Management
Over the past year, NASA continued to make progress in
improving its internal control over financial reporting by executing its
Continuous Monitoring Program (CMP). The CMP assesses and evaluates internal
controls, compliance with generally accepted accounting principles, and evidence
used to support that balances and activity reported in NASA’s financial
statements are accurate and complete by requiring Centers to perform a set of
control activities. Throughout FY 2009, the CMP has operated as designed. NASA
has identified exceptions through the execution of the control activities and
has generally tracked and resolved those exceptions in a timely manner.
Although much progress has been made in developing
policies, procedures, and controls to improve NASA’s financial processes and
systems, challenges remain. Specifically, during FY 2009, NASA management and
Ernst & Young LLP (E&Y) continued to identify deficiencies in the
Agency’s system of internal control, which impair NASA’s ability to timely
report accurate financial information. The most severe deficiency involves
NASA’s internal control over legacy property, plant, and equipment (PP&E).
As shown in the following table, this deficiency has been reported as a
material weakness for several years.
The
following is especially important. From page 11:
Standards of Ethical Conduct Compliance. There is a great
deal of interaction between NASA and the private sector, including both
industry and academia. Again, given that approximately 90 percent of NASA’s
budget is dedicated to contracts and grants, there is great incentive for
private sector interests to influence NASA employees. There is also substantial
interaction between NASA’s scientists and researchers and those working for
non-governmental entities, and incentives abound for such acts as sharing
information that is sensitive but unclassified. Many NASA employees often seek
to pursue financial opportunities in the private sector beyond their Government
employment. With the interchange of talented personnel between the public and
private sectors, the advent of term appointments, the use of Intergovernmental
Personnel Act appointments, and the use of contractors to meet personnel needs,
management is challenged to ensure that ethics laws and regulations applicable
to each category are identified and followed. It is imperative that NASA
employees, as stewards of NASA’s mission and budget, are aware of and comply
with the applicable ethics laws and regulations.
However,
Margolin filed a Freedom of Information Act Request on December 14, 2009. (See Ref5_f2_01.pdf and Ref5_f2_01a.pdf).
One of his requests was
11. Please send me documents relating to
a standard of ethics or conduct for NASA contractors.
NASA’s
tardy response to that item (Ref6_jm_nasa_foia2_response.pdf),
received February 16, 2010 was:
The link
to Federal Acquisition Regulations produces an interesting document (Ref7_08-12.pdf):
December 22, 2008
CONTRACTOR ETHICS
PURPOSE:
This Procurement Information Circular (PIC) is issued to call attention
to the new contractor ethics requirements and to advise acquisition personnel
of their roles and responsibilities in implementing the programs and processing
reports of violations under the program.
BACKGROUND:
Over the past year, two significant FAR rules related to contractor ethics have
been issued. In November of 2007, the FAR was revised to require
contractors to establish a written code of business ethics and conduct.
Furthermore, on December 12, 2008, the Contractor Business Ethics Compliance
Program and Disclosure Requirements went into effect, requiring contractors to
report criminal violations and overpayments.
Under the fist{sic} rule,
contractors are required to:
- Establish a
written code of business ethics (FAR 52.203-13)
- Establish an
internal control system that facilitates timely discovery of improper conduct
in connection with Government contracts and ensures that corrective action is
taken.
- Train their
employees in business ethics; promote business ethics awareness
The second rule builds upon the
first by additionally requiring contractors to:
- Timely
disclose any violations of Federal criminal law involving fraud, conflict
of interest, bribery, or gratuity violations found in Title 18 of the United
States Code; or a violation of the civil False Claims Act (31 U.S.C. 3729-3733)
to the Agency Office of the Inspector General, with a copy to the contracting
officer.
- Timely disclose
and remit any significant overpayments made by the Government.
Therefore:
1.
Contractors have to agree to disclose any violations of specified
Federal criminal laws that they commit.
2.
Contractors have to come up with their own written code of business
ethics.
If NASA requires (allows) Contractors to write their own
business ethics code, and there is no standard for judging the adequacy of the
Contractor’s ethics code, then NASA does not have a business ethics code for its
Contractors.
Reference 4 (NASA 2009
Management Challenges) refers to a Standards of Ethical Conduct Compliance for
NASA employees. However, NASA employees are working with Contractors who set
their own code of ethics.
5. As of February 2010 NASA has still failed to
get its financial house in order. NASA’s auditor refused to sign-off on its
latest audit.
Reference 8 - GAO United States Government
Accountability Office Testimony Before the Subcommittee on Space and
Aeronautics, Committee on Science and Technology, House of Representatives - NASA
Key Management and
Program Challenges, Statement of Cristina Chaplain, Director Acquisition
and Sourcing Management, February 3, 2010 - http://legislative.nasa.gov/hearings/2-3-10%20CHAPLAIN.pdf {Click here for Local Copy}
From page 7:
NASA has continually struggled to
put its financial house in order. GAO and others have reported for years on
these efforts.7 In fact, GAO
has made a number of recommendations to address NASA’s financial management
challenges. Moreover, the NASA Inspector General has identified financial
management as one of NASA’s most serious challenges. In a November 2008 report,
the Inspector General found continuing weaknesses in NASA’s financial
management process and systems, including internal controls over property
accounting. It noted that these deficiencies have resulted in disclaimed audits
of NASA’s financial statements since fiscal year 2003. The disclaimers were
largely attributed to data integrity issues and poor internal controls. NASA
has made progress in addressing some of these issues, but the recent disclaimer
on the fiscal year 2009 audit shows that more work needs to be done.
Here is footnote 7:
7 GAO, Property Management: NASA’s Goal of
Increasing Equipment Reutilization May Fall Short without Further Efforts, GAO-09-187
(Washington, D.C.: Jan. 30, 2009); GAO; Business Modernization: NASA Must
Consider Agencywide Needs to Reap the Full Benefits of Its Enterprise
Management System Modernization Effort, GAO-07-691 (Washington, D.C.: July 20,
2007); and GAO, Financial Management Systems: Additional Efforts Needed to
Address Key Causes of Modernization Failures, GAO-06-184 (Washington, D.C.:
Mar. 15, 2006).
6. NASA Administrator Bolden found it necessary
to issue a centerwide communication ordering all NASA personnel to cooperate with OIG
investigations and audits.
Reference 9 - This is
from SpaceRef: http://www.spaceref.com/news/viewsr.rss.html?pid=33246
Although the article gives a link to the NASA HQ web site
General Bolden’s announcement does not seem to be there.
Message from Administrator Charles
F. Bolden, Jr. - January 14, 2010 Transparency, Communication and Cooperation
STATUS REPORT
Date Released: Thursday, January
14, 2010
Source:
NASA HQ
Subject:
Message from Administrator Charles F. Bolden,
Jr. - January 14, 2010 Transparency, Communication and Cooperation
From:
Centerwide Announcement
Date:
Thursday, January 14, 2010
Message from Administrator Charles
F. Bolden, Jr. - January 14, 2010 Transparency, Communication and Cooperation
President Obama has made it clear
that he is committed to a more transparent and responsive Federal Government. I
believe that NASA should be a leader in implementing that goal. Accordingly,
whether we are referring to the Agency’s treatment of requests under the
Freedom of Information Act, answering questions from Congress or cooperating
with our Inspector General in Agency audits or investigations, I expect that we
will respond both promptly and thoroughly.
As I know you realize and I hope
you appreciate, the NASA Office of Inspector General (OIG) performs a valuable
function at the Agency with both its audits and its investigations. I fully
support the OIG’s efforts to eradicate fraud, waste and abuse, as well as its
role in making the Agency more efficient and more effective. While cooperation
with OIG audits and investigations is mandated by Federal laws and regulations,
NASA employees should readily and fully cooperate whenever an OIG
representative seeks access to personnel, facilities, records, reports,
databases, or documents because it is the right thing to do. Leadership should
also ensure that no unduly burdensome requirements are imposed on OIG auditors
or investigators carrying out their important duties. We also need to
understand that while OIG personnel generally will state the reason for their
requests, they are under no obligation to do so and sometimes cannot do so.
The OIG also serves as the point of
contact for NASA employees to report possible criminal activity, fraud, waste,
abuse and mismanagement involving Agency funds or employees.
As we begin this new decade, let’s
renew our commitment to strengthening NASA’s traditional values of openness,
honesty and transparency.
With best regards for the New Year,
Charles F. Bolden, Jr.
___________________________________________________________________________________
Let’s see if General Bolden and Deputy Administrator Garver can get
NASA’s house in order.
Jed Margolin
Virginia City Highlands, NV
March 7, 2010